William Austin School 

Project Type 

Mechanical 

Date & Duration 

Sep 2021 - 6 weeks

Financial Value 

£235,000

Client 

Luton Council

Picture2.jpg

We completed the installation of a new plant room at William Austin School within a tight six-week window during the summer holidays. This accelerated timeline presented several constraints, including limited access to the site, strict deadlines to ensure systems were operational before the new term, and coordination with other trades working simultaneously. Despite these challenges, we delivered a fully functional plant room housing heating and ventilation systems, ensuring seamless integration with the new build and existing infrastructure, all while maintaining high standards of safety and quality.

Services

- Installation of 3 x 320kW Boilers 

- 2 x 500L cylinders

- 960kW Plate heat exchanger 

- BMS System with heatmeters and Trend IQView 4 controller

- Fully insulated

- Leak detection system