Merebrook Infant School
Project Type
Electrical & Mechanical
Date & Duration
Aug 2023 - 6 weeks
Financial Value
£210,000
Client
Baily Garner & MK Council

We were tasked with installing a new air conditioning system at Merebrook School, where the unique architecture of the building required a tailored approach. Our team worked closely with the design to ensure the installation complemented the existing aesthetics, selecting discreet units and routing services in a way that preserved the character of the space. The result was a seamless integration of modern climate control that met both functional and visual expectations. We also carried out builders’ works to construct a new acoustic enclosure for the air source heat pumps. This enclosure was designed to reduce noise impact while blending into the surrounding environment, further enhancing the functionality and visual harmony of the site.
Services
- Installation of new Mains panel
- Stripout of existing heating system
- Installation of new 4 x Daikin external condesnsers to serve AC system throughout the school
- New boxing installated around pipework
- Fire stopping
- New cable tray installation
- New enclosure for ASHPs
- Testing & comissioning